Project Timetable
| May (2005) |
Utility relocation |
| June |
Excavation, rock removal, and foundation |
| July |
Construction begins; both projects |
| February (2006) |
Seegers Union Addition completed |
| May |
Seegers Union renovations begin |
| August |
New Sciences Building completed; renovation of Shankweiler begins; Seegers Union renovations completed |
| September |
Construction of sciences tower and bridge section begins |
March (2007) |
Renovation of Shankweiler upper floors completed |
| March |
Renovation of Shankweiler lower floors completed; tower and bridge sections completed |